This week we will be transitioning back into the classroom from the farm/garden area. We will be spending a max of two days in the garden area.

With that said we received some surprising arrivals, particularly the arrival of consumable products in the form of wood!

Friday: Two chicks hatched and the Tuff Sheds were installed! Today we were back outside. Installed 4x4 post for the bachelor pad.



Thursday: Rain. We are indoors. Begin iMovie project. 10 images, transitions, titles and movies.
OA  Dam Building.


Wednesday: Placed the beam for the bachelor pad to support the roof. Also began some modifications to the back end of the storage container to allow for the placement of some equipment. OA

Tuesday: Continued the construction of the chicken bachelor pad. We poured concrete for two posts.
No OA

Soccer Match HHS vs SA



Monday: Received 2x4, 2x6, &plywood delivery. Placed materials in both the shipping container and the Hawks Nest temporarily until sheds come, at moment do not have a date for their installation.